ACT III REMODELING PROJECT - CONSTRUCTION UPDATES
Check back here often for updates on our construction progress.
3/18/2022: Our new seats are all in and just waiting for YOU!
New Box Office and Concessions area is taking shape!
2/21/2022: Time to install all 195 of our new seats!
2/10/2022: The lobby now has carpet!
2/4/2022: Hearing Loop Installed
In between the concrete and the future carpet, is our new state-of-the-art Hearing Loop assistive listening system. (Protected with red tape in this image.) This technology will enable audience members with telecoil-equipped hearing aids to simply flip a switch on their hearing aid to have the show's sound delivered directly through their hearing aids. |
1/21/2022: Auditorium Work
The auditorium has been painted and special acoustic panels hung. Next up is the installation of our new Hearing Loop system. Meanwhile, crews have been installing our new stage rigging system.
The auditorium has been painted and special acoustic panels hung. Next up is the installation of our new Hearing Loop system. Meanwhile, crews have been installing our new stage rigging system.
1/17/2022: Paint and Tile in the Bathrooms
We know we're getting close to the finish line when the painters have arrived!
We know we're getting close to the finish line when the painters have arrived!
12/15/2021: Feature Ceiling in Lobby
Check out the new wood feature ceiling in the Box Office and Concessions end of the lobby.
Check out the new wood feature ceiling in the Box Office and Concessions end of the lobby.
12/6/2021: Adding sheet rock
The new community room -- which will be a space for meetings, receptions, play readings, etc. -- is beginning to take shape!
The new community room -- which will be a space for meetings, receptions, play readings, etc. -- is beginning to take shape!
12/3/2021: New Audience Entrance
This week we poured concrete for the new entrance plaza. (Sending huge thanks to Starfire Lumber for the donation of those beautiful beams holding up our new entryway!)
This week we poured concrete for the new entrance plaza. (Sending huge thanks to Starfire Lumber for the donation of those beautiful beams holding up our new entryway!)
11/22/2021: Adding Insulation
This week crews installed insulation throughout the lobby area, just in time for our colder weather! Pictured below is the new men's restroom. Hopefully we can turn the heat back on in the building soon. . . .
This week crews installed insulation throughout the lobby area, just in time for our colder weather! Pictured below is the new men's restroom. Hopefully we can turn the heat back on in the building soon. . . .
11/15/2021: Reinstalling steel beams above stage
We brought out the big crane! We are reinstalling the steel beams (that hold our stage rigging) in their new higher position.
We brought out the big crane! We are reinstalling the steel beams (that hold our stage rigging) in their new higher position.
10/15/2021: Raising the Tower
The tower over our stage is being raised, to accommodate the new stage rigging system required for our higher proscenium opening. (That enlarged proscenium opening is needed now that the back row of seats is higher.)
The tower over our stage is being raised, to accommodate the new stage rigging system required for our higher proscenium opening. (That enlarged proscenium opening is needed now that the back row of seats is higher.)
9/23/2021:
9/15/2021: Concrete Pouring
8/20/2021:
8/13/2021:
7/27/2021:
6/22/2021:
Video at right:
Genie lift in action, to get workers high enough up to inspect the rigging beams above our stage. |
|
6/4/2021:
5/21/2021: Lots of big, noisy machine action this week!
5/14/2021: This week we excavated to make room for the new lobby bathrooms.
|
(Left) Watch the excavation team at work clearing the way for the new lobby entrance at the front of the building.
|
5/5/2021: Visible changes are happening daily. Here are a few highlights from the last week.
4/23/2021: Demolition is underway! This week our construction team began the work to raise the proscenium opening. (This is necessary to ensure that audience members in the soon-to-be-higher back row have a full view of the action on stage!) They also removed siding from the exterior portions of the building where modest new additions will go, and removed the lobby bathrooms. (The bathroom space will become part of the new lobby, and new bathrooms will be built along the north side of the building.)
Above: The proscenium opening is being raised two feet, so that everyone in the soon-to-be-higher back row will be able to see all of the action on stage.
3/13/2021: Volunteer crews disassemble our Mamma Mia set and move it into a trailer for temporary storage. (We were just about to open Mamma Mia when COVID hit in March 2020. We hope to finally get our Mamma Mia cast back on stage after the remodel and as soon as COVID guidelines permit such large group gatherings.)
|
|
3/6/2021: The pre-construction work parties are underway. Check out the video to the left to see our progress. COVID precautions make things a little more complicated, as right now we can only have small groups of masked volunteers working at a time, but we'll still get the job done!
|
2/27/2021: On the heels of the very exciting news that the M.J. Murdock Charitable Trust approved a large grant for this project, we are beginning the pre-construction move-out process. We need to remove all sound and lighting equipment from the booth, and all seats from the auditorium, so the contractors can do their magic. The M.J. Murdock Charitable Trust joins the State of Oregon, Ford Family Foundation, Woodard Family Foundation, Oregon Community Foundation, Sunderland Foundation, and Oregon Cultural Trust -- along with hundreds of individual donors -- in providing major support for this project. We are not yet at 100% of our fundraising goal, but the Murdock grant brings us to about 95% of the way there, which is enough to get construction started.
|